This help article applies to users on Fresh Projects Version 1.
Which version of Fresh Projects am I using?
00:00: A Purchase Order can be raised in Fresh Projects to confirm an agreement to pay a
00:04: supplier for a set amount.
00:06: You are then able to track your spend against the Purchase Order as expenses are
00:11: incurred.
00:13: Let's take a look at how to generate a Purchase Order...
00:17: In the Main Menu, click "Capture"
00:21: Then,
00:21: click the "Purchase Order" tab.
00:25: Click "New Purchase Order" to start creating a new purchase order.
00:30: Using the dropdown icon,
00:32: specify the Expense Type for your Purchase Order.
00:36: Then, click "Add Project" to link the purchase order to a specific project.
00:42: Select your Project.
00:45: Then,
00:46: select your Sub-project.
00:49: Finally,
00:50: click "Add".
00:52: In the Supplier field,
00:54: start by typing the name of your supplier and then select your supplier from the
00:57: dropdown.
01:00: Please note that you need to have a contact already set up in Fresh Projects as a
01:04: "Supplier" type.
01:05: This can be set up under Contacts.
01:09: In the PO Reference box, enter the purchase order reference number.
01:15: You can also upload your relevant PO quotation document.
01:20: You can also populate any purchase order notes,
01:23: such as delivery notes.
01:26: You can also add a further description to be included on your purchase order
01:30: document.
01:32: Additionally,
01:33: you can add any internal notes for visibility to your internal team
01:38: Click "amount" to enter the value for the purchase order.
01:43: Then, click "Submit" to save and submit the purchase order for approval.
01:48: Navigate to the "Approvals" in the Main Menu.
01:52: Click "Load" to retrieve the latest approval data.
01:57: Now,
01:57: click on the "Purchase Orders" Tab to view the list of purchase orders awaiting
02:02: approval.
02:04: Here you will see your latest purchase order waiting approval.
02:09: Click the tick icon to select your purchase order.
02:13: Click "Submit" to approve your purchase order.
02:17: You can now navigate to the "Time and Expense Explorer".
02:22: Click the "Purchase Orders" tab to manage and review all purchase orders.
02:27: Now,
02:28: select your date range to display all relevant purchase orders captured within this
02:32: time range.
02:35: Then,
02:35: click "Load".
02:38: Here,
02:39: you will be able to view all details pertaining to your purchase order.
02:44: If any changes need to be made to the amount,
02:46: click on the pencil icon to edit the amount.
02:50: Here you can download your Purchase Order template in Word or PDF format,
02:55: which you can then send directly to the supplier.
02:59: If you do not see these icons available,
03:01: please contact our Support Team so that we can load a PO template into your account.
03:08: Now proceed with navigating to your project,
03:11: and clicking on the "Budget and Fee" tab.
03:15: Under the Purchase Orders column,
03:17: you are able to clearly see the amount that has been raised for Purchase Orders for
03:21: your relevant sub-project.
03:24: Let's take a look at how to allocate a Purchase Order...
03:28: Click "Capture" in the Main Menu.
03:32: Then, click the "Expenses" tab.
03:35: Using the dropdown icon,
03:37: specify the Expense Type.
03:40: You will need to ensure the expense type matches the expense type specified on your
03:44: purchase order.
03:46: Click "Add Project" to link the expense to a specific project.
03:51: Select your Project.
03:55: Then,
03:55: select your Sub-project.
03:59: Finally,
03:59: click "Add".
04:02: In the Supplier field,
04:03: start by typing the name of your supplier and then select your supplier from the
04:07: dropdown.
04:09: You will need to ensure that your selected supplier matches the supplier from your
04:12: Purchase Order.
04:15: You will then get a pop-up for Purchase Orders,
04:18: where you can select your relevant purchase order from the dropdown
04:22: Here you can click 'Upload Receipts' to add any supporting documents to the expense.
04:28: You can also populate any additional notes to your Expense.
04:34: Click "View Purchase Order" to examine the full purchase order information.
04:39: You will then get a pop-up displaying your original purchase order for your
04:43: reference.
04:45: Click "amount" to enter the value for the Expense.
04:50: Finally,
04:50: click "Submit Expenses" to finalize and send your expense for approval.
04:56: Navigate to the "Approvals" in the Main Menu.
05:00: Click "Load" to retrieve the latest approval data.
05:04: Now, click on the "Expenses" Tab to view the list of expenses awaiting approval.
05:11: Click the tick icon to select your Expense.
05:15: Click "Submit" to approve your Expense.
05:18: You can now navigate back to the Time and Expense Explorer,
05:22: and back to the "Purchase Orders Tab".
05:25: Here you can locate your Purchase order.
05:29: You can now clearly see how much of your PO you have allocated to actual expenses.
05:35: The remaining portion will indicate how much your supplier can still invoice you.
05:40: You can now navigate back to your Project.
05:43: Under the "Actual Cost" column,
05:45: you are able to clearly see the amount that has been allocated to expenses.
05:50: This allows you to track your spend against the Purchase Order as expenses are
05:54: incurred.
05:56: You have now successfully captured and reported on your Purchase Order in Fresh
06:00: Projects.