This help article applies to users on Fresh Projects Version 2. 
Which version of Fresh Projects am I using? 


00:18: Click "Capture" in the Main Menu.

00:22: Then,

00:22: click "Timesheets".

00:25: To add any planned work into your timesheet,

00:27: click "Add Row".

00:30: Click "Planned" to view all projects and sub projects for which you have been added as

00:35: a resource.

00:37: Click the drop down for the project you have been assigned, to view the respective

00:41: sub-projects

00:43: Click here to select the subproject of the assigned Project.

00:48: Click "Save selection" to confirm and save your timesheet choices.

00:53: You can now capture your time accordingly against the respective project and

00:57: sub-project.

00:59: To see the number of hours assigned to you,

01:02: click on the traffic light icon.

01:05: A pop up will then communicate the number of hours assigned to you for that

01:09: project and sub project next to the Budget, while the actual hours you've spent on it

01:14: thus far will reflect next to Actual.

01:17: You can now complete and submit your timesheet as usual.

01:21: You have now learned how to navigate your assigned projects and sub-projects within

01:25: your timesheet dashboard.