00:00: The Project Planner is a resource management tool that lets you allocate and track
00:04: resource capacity across your projects and sub
00:08: projects. Lets take a look at how to set it up...
00:11: Firstly,
00:12: select "Projects" from the main menu.
00:16: Then select "Project Planner".
00:19: In the top half of the project planning dashboard you will find a list of all your
00:23: projects.
00:26: And in the bottom half you will find your list of resources.
00:31: You can then filter the tracking metrics to be shown as either the budgeted cost
00:35: value or budgeted hourly value.
00:38: Next,
00:39: you can adjust your project planner dashboard view to show the project over a
00:43: certain chosen timeline,
00:44: this can be done by adjusting the timeframe in the dashboards top right hand drop-down
00:48: menu.
00:51: You can also set a custom date range by inputting the desired start and end dates
00:56: within the "Date Range" drop-downs at the top of the dashboard.
01:00: Once you have adjusted the time frame to your preference,
01:03: the time will be displayed in weekly columns.
01:06: On the left side, the past two weeks will be indicated by a blue line and a greyed-out
01:11: appearance.
01:13: Following the blue line,
01:14: you will see the present and future weeks.
01:18: Next, you can search for the specific project you want to allocate resources toward
01:23: by searching the project name or code in the search bar.
01:26: You will notice that the resources also has its own search bar to do the same.
01:32: Alternatively, you can filter the "Projects" view by selecting the settings cog icon
01:37: next to the search bar and configuring the available filters to display the specific
01:41: projects.
01:44: After configuring the filters,
01:46: select "Done" to apply the changes.
01:49: Similarly,
01:50: you can click the settings cog icon next to Resources to group by Job categories or
01:55: by your Tracking categories.
01:58: Next,
01:59: you can expand the project view by selecting the arrow icon next to the project
02:02: name.
02:05: The expanded view will show the stages,
02:07: groups and sub projects that form part of the selected project.
02:12: The expanded view will also show the hours or costs that have been budgeted toward
02:17: each sub-project based on which filter you have toggled.
02:21: Figures appear in either green or red to indicate budget status.
02:26: Green figures show the available hours left to allocate.
02:30: While red figures indicate that more hours have been allocated than were originally
02:34: budgeted,
02:35: indicating that the sub project is currently over-budget.
02:40: Now,
02:40: if you click on the green figure for a particular sub
02:44: project, you can then click "Add budgeted hours".
02:47: This will allow you to add the budgeted hours as set in the Project Budget.
02:52: The Planner will then automatically populate and distribute the hours over the
02:56: period defined within the budget.
03:00: If you want to manually assign hours,
03:02: click on the "+" sign under the week column,
03:04: where you want to assign the resource.
03:08: Then, click "Add resource".
03:11: You can then search for the resource or employee you would like to assign.
03:16: Then select the percentage of time per week you want your resource to spend on this
03:20: sub-project.
03:23: Alternatively,
03:24: you can set the amount of hours per week
03:26: you would want your resource to spend on this subproject.
03:30: You can then set the total amount of weeks you want this resource to work.
03:36: You are also able to swap out resources by selecting the double-arrow icon next to the
03:40: resource name to swap out that resource for another.
03:45: Alternatively,
03:46: you can also search for your resource and drag and drop their icon into the planner.
03:52: You are able to add multiple resources to your sub-project from this view.
03:56: Once you have added all resources,
03:59: you can go ahead and select "Done".
04:02: Alternatively, after you have entered the resource's percentage of time allocation,
04:07: or the amount of hours needed per week,
04:09: you can simply drag the resource icon to adjust the amount of weeks required for
04:13: your sub-project.
04:16: You can then continue resource planning for all remaining sub projects within
04:20: your project.
04:22: In the bottom half of the screen you can view each individual resource's planned
04:26: utilisation rates,
04:28: with different color indicators for the level of utilization.
04:32: This figure also accounts for Public Holidays planned for the employees leave
04:36: region,
04:36: as well as approved leave time.
04:39: This helps you ensure you do not inadvertently schedule out a resource when they
04:43: are not available.
04:46: You can also click on a particular resource's week.
04:50: This will display a pop-up showing what projects,
04:52: sub
04:54: projects, and bank holidays are allocated for that week.
04:58: For each sub project, there are some additional features you can use.
05:02: There is an option to add milestones, which allows you to enter the date of
05:06: particular time-based milestones.
05:10: The milestone additions will appear as lines in your project planner,
05:14: indicating the date they were established for the selected time-based task.
05:19: There is also an option to download an image of this particular project, which could
05:23: be used to show a client the project timeline you have planned.
05:28: Lastly, there is an option to download the project resource planning in an excel
05:33: format.
05:35: Alternatively, if you would like to download the entire resource planning report as
05:39: an excel sheet,
05:40: this can be done by selecting the downward facing arrow icon at the top of the
05:44: dashboard.
05:46: To focus solely on the projects section of the project and resource planner,
05:50: select the view adjustment option located at the top right corner of the planner
05:55: dashboard.
05:56: By choosing this option, the resource list view will be minimized, allowing the
06:00: project section to expand.
06:04: Alternatively, if you wish to focus exclusively on the resource section of the
06:08: project and resource planner,
06:10: select the opposite view adjustment option.
06:13: Consequently, the project list view will be minimized,
06:16: allowing the resource section to expand.
06:20: Lastly, if you wish to split the view evenly again,
06:23: that can be done by selecting the split view option.
06:27: You now know how to successfully adjust, allocate and schedule resources in the
06:32: Project Planner.