00:00: This article explains how to import budgets within the Freshprojects Professional application.
00:04: application.
00:01: This article outlines the process for importing budgets directly from the Project
00:05: Planner.
00:06: Begin by planning your resources in the Project Planner and ensure to save your
00:10: changes.
00:13: Navigate to your project, then select the "Budget and Fee" tab.
00:18: An orange indicator will appear to signify that the planning in the project planner
00:22: does not align with the current project budget.
00:27: Open the budget editing options and select the "update budget with recent external
00:31: changes" feature.
00:34: Click "Import Budgets" to initiate the process of importing the planned resources into
00:39: the project budget.
00:42: Here,
00:43: you can view your original budget alongside the changes imported from the project
00:47: planner.
00:48: Select "future planned" to proceed with making the changes.
00:54: Click "Done" to finalise the budget import.
00:58: You have successfully imported budgets into a project using Freshprojects Professional
01:02: by navigating through the project dashboard and selecting the appropriate
01:05: import options.
01:08: For more information,
01:09: refer to related articles on budget management and project setup within Freshprojects.
01:14: projects.